BUET-IWFM

ADVISORY SERVICE

INTRODUCTION

One of the missions of the Institute is to provide expert advisory services to government and non-government organizations. Through consultancy and advisory services, the Institute has used its experience and expertise in seeking solutions to real life problems. This has allowed the organizations working in relevant fields to use the expertise available at the Institute. The faculty members of the Institute have been involved in over 100 consultancy and advisory services.

3

Projects Done

With

1

Organizations

PROJECT LIST

  • Padma Bridge Rail Link Project (PBRLP) (with Department of Civil Engineering and Department of Water Resources Engineering)

    Client: Bangladesh Railway through Construction Supervision Consultant (CSC), Bangladesh Army

    Project Duration: July 2018 - June 2021

  • Development of Master Plan for Payra Port (with Department of Civil Engineering)

    Client: Payra Port Authority

    Project Duration: July 2019 - June 2021

  • Developing Institutional Framework for Flood Preparedness Programmes (FPP)

    Client: MoDRM under National Resilience Program

    Project Duration: November 2019 - October 2021

  • Review of Design for BN Naval Base (BNS Shiekh Hasina) (with Department of Civil Engineering)

    Client: Bangladesh Navy

    Project Duration:

  • Review of Design for Chittagong- Cox’s Bazar Expressway (with Department of Civil Engineering)

    Client: Roads and Highway Department

    Project Duration: January 2021 - 30 June 2021

  • Technical Support Service for the Engineering, Procurement and Construction Including Installation and Commissioning of a Complete Ship Docking and Repair Facility (with Department of Civil Engineering and Department of Naval Architecture and Marine Engineering)

    Client: Bangladesh Navy

    Project Duration:

  • Carrying Out Climate Inclusive Inundation Modelling for Gaibandha Sadar under Gaibandha Strategic Development Plan

    Client: BRAC UDP and Urban Development Directorate, MoHPW

    Project Duration: 01 November 2020 - 03 January 2021

  • Developing Cyclone Amphan and recent Flooding Recovery Plan and its implementing strategy

    Client: United Nations Development Programme (UNDP)

    Project Duration: 26 December 2021 - 31 July 2021

  • Water Quality Monitoring of water courses located in transboundary/shared catchments in Bangladesh

    Client: World Bank

    Project Duration: January 2021 - December 2021

  • “Feasibility study for installing and operating cable car and preparation of Master Plan for Madhobkundo Eco park” Project

    Client: Department of Forestry

    Project Duration: 09 March 2021 - 30 June 2021

  • Pilot Programme to Improve Management of Flood Control, Drainage and Irrigation Projects: Phase I

    Client: Bangladesh Water Development Board (BWDB) and The Ford Foundation,

    Project Duration: 1989-91.

  • Review and Optimization of Planning and Design of Irrigation and Drainage System of Teesta Barrage Project

    Client: Bangladesh Water Development Board (BWDB),

    Project Duration: 1989.

  • Surface Water Simulation Modelling Programme

    Client: United Nations Development Programme (UNDP) and World Bank,

    Project Duration: 1988.

  • Surface Water Simulation Modelling Programme, Phase I, UNDP Project BGD/85/045

    Client: Master Plan Organization, Ministry of Irrigation, Water Development and Flood Control,

    Project Duration: 1986-1988.

  • Review and Optimization of the irrigation and drainage system of the Teesta Project

    Client: Bangladesh Water Development Board (BWDB),

    Project Duration: 1987-1988.

  • Surface Water Simulation Modeling Program, Master Plan Organization

    Client: Ministry of Irrigation, Water Development and Flood Control, Government of the People's Republic of Bangladesh,

    Project Duration: September 1985 - August 1988.

  • Mathematical model study of the River Karnafuli

    Client: Chittagong Port Aurhority,

    Project Duration: 1984-1986.

  • Study of Shifting Pattern of Jamuna River and Recommendation for Protection to Caissons of the East-West Interconnector, Jamuna River Crossing

    Client: Bangladesh Power Development Board (BPDB),

    Project Duration: 1983-1985.

  • Expert services for civil repair works of the Karnafuli Hydrostation, Kaptai

    Client: Bangladesh Power Development Board (BPDB),

    Project Duration: 1983-1984

  • Modelling of salt water intrusion in the Meghna Delta

    Client: Expert Study Group, Ministry of Agriculture

    Project Duration: 1983